Specifications
  • 94 Kitchens
  • 6 kitchen unites per week

Value : £750k

Programme : 22 Weeks

Size : 94 Kitchens

Delivering 6 kitchen unites per week, across Leicester and Cambridge, this 5-month programme for Riverside Housing Association requires the full re-wiring and LD2 upgrades to fuse boards, CO2 & smoke detection systems, as well as the installation of new extraction and lighting.

Sequence of works:

  • Relocation of Appliances and Fittings
  • Strip-out (inc. wall tiles, pipe boxing & decorations)
  • Installation of new kitchen units
  • Fit pipe boxing
  • Renew existing hot and cold water supply
  • Install Sure Stop
  • Undertake Electrical Condition Report (Periodic Test)
  • Install new power ring main & cooker circuit
  • Renew kitchen light fitting & extractor fan
  • Install Heat Detector
  • Fit new wall tiling, vinyl floor covering and new plaster finish
  • Install CO2 alarm with radio bases and smoke alarm